Procedure
- Permit Difficulty High
A procedure that allows a business, activity or stay that the law generally restricts, after review; licenses fall into this type. The authority reviews facility standards, location and consultation with other agencies, and a permit can be refused if the standards are not met.
- 01
Confirm whether a permit is required: list the class, product name and maximum quantity of hazardous materials to be stored or handled, calculate the multiple of the designated quantity, and determine which type of facility applies, such as a manufacturing facility, indoor storage, tank storage or general handling facility. Storage for residential heating and storage of 20 times or less of the designated quantity for agricultural, livestock or fisheries heating or drying facilities may be installed without a permit.
- 02
Review technical standards: use the layout plan to check whether safety distances and clearance space, building structure, ventilation and exhaust equipment, and fire extinguishing, alarm and evacuation equipment meet the location, structure and equipment standards of the Enforcement Rule. For facilities subject to technical review, obtain the Korea Fire Industry Technology Institute review first and attach the result to the permit application.
- 03
Prepare the permit application: attach to the application on Form No. 1 or Form No. 2 of the Enforcement Rule of the Safety Control of Hazardous Substances Act the drawings showing site layout, equipment layout and process outline, and electrical, lightning protection, fire extinguishing, alarm and evacuation equipment, together with the structural equipment specification sheet for the facility, and submit it to the competent fire station.
- 04
Construction and tank inspection: proceed with construction after the permit, and if there are hazardous materials tanks, obtain the tank safety performance inspection and keep the pass certificate. For piping subject to pressure or non-destructive testing, keep the test pass documents in preparation for the completion inspection.
- 05
Apply for the completion inspection: after installation, apply using Form No. 22 or Form No. 23 with the piping test pass documents and tank inspection pass certificate attached, and use the facility only after receiving the completion inspection pass certificate.
- 06
Appoint the safety manager and ongoing management: appoint a qualified safety manager for each facility and report the appointment within 14 days. If the safety manager is dismissed or resigns, appoint a new one within 30 days and designate a deputy to perform the duties in the meantime.
Filing route
Filing route
Confirm the current filing office, jurisdiction, and online availability on the official website.
Official checkDeadlines & processing notes
Deadlines & processing notes
Fees & official charges
Fees & official charges
Included in the basic fee — Initial document review, required-document guidance, basic form preparation, one filing support and responses to up to two supplement requests.
Conditional success fee — For this service, any conditional success fee may be separately agreed within the lawful service scope and stated in a written engagement agreement. No outcome is guaranteed.
Displayed amounts are starting estimates, not statutory or standard rates. The final fee is confirmed after consultation and document review in the engagement agreement. Government fees and actual expenses may change.
Fees & official charges →Basic documents
Basic documents
위험물(제조소, 저장소, 취급소) 설치허가신청서(별지 제1호서식)
Scope of services
Scope of services
Hwang Yunsang Administrative Agent Office prepares and translates documents for administrative agencies, submits them on your behalf, and guides you through permit, application, and notification procedures. Services that require the principal’s personal appearance, principal’s application, or electronic signature may be limited in delegation.